Project Update for Harmony 005
The first delivery scheduled within West Chester is 10/18/2023. Starting week of 10/23/2023 there will be a crew onsite to start installing the poles.
The contractor is in the process of working their way down from West Goshen to the West Chester area to begin construction. Our contractor (Infrasource) is going to start coordinating the pole deliveries within the next week or so.
The yellow pins (below) represent individual pole locations where IFS will be preforming work. The red pins are Verizon poles. The pins themselves don’t necessarily represent a pole replacement. With that being said, below is a breakdown of where poles would be dropped off within West Chester Borough.
The anticipation is to prioritize setting poles that will affect the homeowners everyday life. We wanted to provide a courtesy notice in advance.
*600 Walden Dr is at location 104 and will not be directly affected, but will have visibility of poles when they leave their driveway.

Sheet 4
3 – 60/2 (Locations 35, 33, 32)
Sheet 3
1 – 60/2 (Location 26)
2 – 50/2 (Locations 89, 92)
2 – 45/2 (Locations 90, 91)
Sheet 16
8 – 45/2 (Locations 93 – 98, 100, 101)
1 – 50/2 (Location 99)
Sheet 18
4– 45/2 (Locations 110 - 113)